Details
Developer: Wil Ferrero, 5000 Birch Street, Suite 400, Newport Beach, CA 92660, 949-333-8525 wil.ferrero@clearwaterliving.com
Project Planner: Kim Jordan, Planner III, kjordan@townofwindsor.com, 707-838-5331
Status:
9/19 – 10/19, 2022: 30-day review and comment period on Initial Study Mitigated Negative Declaration (use link to project webpage above to review documents)
8/3/2022: Town Council review of updated development agreement terms
June 2022: Final Traffic Impact Study completed and available on the Town’s Clearwater webpage (link above)
Spring 2022: Applicant resubmittal of application
12/30/2021: Incompleteness letter sent to applicant
10/13/2021: Joint Town Council – Planning Commission joint study session regarding Development Agreement
8/13/2021: Partial resubmittal
7/1/2021: Incompleteness letter sent to applicant
5/13/2021: Formal application submitted
4/22/2021: Environmental review started
3/4/2020: Town Council review of conceptual plans
1/28/2020: Planning Commission review of conceptual plans
10/11/2022 Planning Commission meeting to review Initial Study/Mitigated Negative Declaration
9/19/2022 through 10/19/2022: Comment period on Initial Study/Mitigated Negative Declaration
12/13/2022: Planning Commission recommendation for approval
2/1/2023: Town Council approval
Next Steps: Applicant to submit building permit and improvement plans for review